Visitors Center |
Search
|
language
Contact us

Projects

Facility upgrade plans

Proposed design of the treatment plant upgrade

The Public Health Regulations of 2010 define the required quality of effluents produced at wastewater treatment facilities in Israel. Association management has expedited the implementation of a general plan for the upgrade of wastewater treatment systems at the plant in order to bring it to the level required by these new more stringent standards. Association management has also decided to provide a response to future population growth in the Association’s member cities. The total quantity of wastewater expected in the year 2030 is approximately 150,000 m³ per day.

The design was prepared by the US firm Hazen & Sawyer in conjunction with the Israeli firm Balasha-Jalon Infrastructure Systems Ltd. 

In the framework of the design works, numerous design alternatives for upgrade of the treatment plant were examined, detailed construction and operating cost estimates were prepared for the various alternatives, and a number of pilot installations were commissioned in order to define optimal technologies and dimensions of the various process stages. In addition, detailed tests were performed of all of the existing equipment units at the wastewater treatment plant since a significant part of the process units, other than the pretreatment system, were constructed many years ago and are unsuitable for the modern treatment processes currently being planned.

The upgrade and expansion design for the treatment plant has been approved by the Water Authority, the Ministry of Environmental Protection and the Ministry of Health.

The following is a detailing of the upgrade and expansion design for the treatment plant:

  1. Pretreatment and preliminary sedimentation
  2. Secondary biological treatment
  3. Tertiary treatment including the construction of filtration and disinfection installations
  4. Sludge treatment      
  1. Treatment Plant Upgrade – Stage I
  • Pretreatment and preliminary sedimentation

    • The existing pretreatment system is obsolete and no longer meets the needs of the wastewater treatment plant. Consequently, improvements will be made that will include the construction of a completely new system of mechanical bar screens with two filtration grades – the first grade has a filtration opening of 15 mm, while the other has a filtration opening of 6 mm. The function of the mechanical bar screens is to filter and extract organic waste in the raw sewage.

The new pretreatment installations will be designed for an average flow rate of 150,000 m³ per day and will take peak flowrates into account.

  • The existing sand removal system is obsolete and no longer meets the needs of the wastewater treatment plant. Consequently, a new installation will be constructed that includes four tanks of the appropriate size in which pumps will be installed for removal of sand and grit in the raw sewage.
  • Future expansion to a flow rate of 150,000 m³ per day will be provided through the construction of two additional primary clarifiers.
  • Construction of a new air treatment installation to prevent odor nuisances originating primarily from the pretreatment installations.

In order to meet new requirements for effluent quality, the first stage in treatment plant upgrade will begin with the construction of new filtration and disinfection installations that ensure that the required effluent quality is obtained continuously and safely.

(All suspended solids 10 mg/L; BOD 10 mg/L; E. coli 10 units per 100 mL)

The filtration and disinfection system will include granular gravitational filtration tanks on a 1.8 m thick bed with hypochlorite disinfection. The filtration and disinfection units will be constructed for a flow rate of 150,000 m³ per day.

At the conclusion of the works detailed above, the treatment plant will produce effluents at the required improved quality, suitable for unrestricted irrigation in accordance with regulations. 

  1. Treatment Plant Upgrade – Stage II  
  • Secondary biological treatment

    • A new wastewater treatment module will be constructed with a flow rate of 60,000 m³ per day. The module will be built with a biological nutrient removal (BNR) process that enables the removal of nitrogen and phosphorus in accordance with legal requirements.
    • Modifications and improvements will be made to the existing aeration tanks of Modules 1 and 3. In this framework, the tanks will be converted into a three stage nutrient removalThe improvements will include the replacement of the aeration system currently based on surface aerators with a system based on bubble aeration and fans with the addition of internal circulating systems compatible with this configuration.
    • Following execution of the improvements in Modules 1 and 3, modifications and improvements will be made to Module 2 so that the treatment capacity of the plant will have a capacity of approximately 150,000 m³ per day at the required quality.
  1. Treatment Plant Upgrade – Stage III

Sludge treatment

The sludge treatment system will be upgraded. The improvements that will be made include the addition of a digester tank and changes in the sludge thickening system in order to enable thickening of the primary sludge (which does not currently undergo thickening) together with the surplus biological sludge. New sludge thickening units will need to be added for this purpose.

  1. Cost of the treatment plant upgrade and expansion project

Following completion of the treatment plant upgrade project, effluent quality will meet all of the most stringent regulations for wastewater treatment in Israel including forecast changes.

The designer’s estimated cost of this upgrade as detailed above is NIS 485 million.

Project Details
  • Start Date
  • End Date
  • Cost of the project
  • Work Time
  •   
  •   
  • ₪485,000,000
  • Approx. 12 months
Projects in progress

Computerized archive

The Association has begun a project to set...

Computerization of engineering drawings

Engineering drawings and paper drawings from the 1950s...

New rag grinder

A rag grinder was installed in 2015 replacing...

New generator

A biological sludge treatment process takes place at...

Installation of sleeves

Extensive maintenance works are being performed in the...

Building renovations

The treatment plant is preparing to renovate and...

Power plant motor coolant piping

The Haifa Wastewater Treatment Plant, operated by the...

Basement ventilation system

Five new aeration fans have been installed for...

Upgrade of the drying and thickening installation

Upgrade of the drying and thickening installation The drying...

Refurbishment of the electricity producing generator

Refurbishment of the electricity producing generator The power station...

Installation of thickening machine

Installation of thickening machine In order to adapt the...

Upgrade of digester tanks

A process of decomposition and stabilization of sludge...

Upgrade of computerized systems

The management system has been upgraded, including Priority...

Replacement of pilot piping in the gas...

The pilot piping in the gas flare has...

Additional projects

Refurbishment of Digester Tank No. 1

Digester Tank No. 1 was emptied and refurbished...

New generator

A biological sludge treatment process takes place at...

Installation of thickening machine

Installation of thickening machine In order to adapt the...
Cookies

This website use cookies to improve site functionality, provide you with a better browsing experience, and to enable our partners to advertise to you.

Detailed information on the use of cookies on this Site, and how you can decline them, is provided in our cookie policy.

By using this Site or clicking on “I agree”, you consent to the use of cookies.

נגישות

  • גודל פונטים

מקרא נגישות

לתאימות מלאה יש להשתמש בדפדפנים כרום ופיירפוקס
למעבר בין אלמנטים בדף לחץ על מקש ה - Tab, לחזרה אחורה לחץ על צרוף המקשים - Shift + Tab

בכלי נגישות זה ניתן לבצע מספר דברים

  • - להחליף צבעוניות של האתר במחלקת הצבעוניות
  • - להגדיל ולהקטין פונטים ללא שבירות עיצוביות
  • - להדגיש כותרות ולינקים בקו מתאר תחתון
  • - ניתן גם לעבוד מקלדת בלבד ולגלוש באתר
  • - ניתן להפעיל מסמך ללא עיצוב כלל
  • - ניתן לאפס הכול לברירת המחדל

ניתן להגיע למקומות עיקריים בקלות ע"י צירופי המקשים הנ"ל

  • ESC מאפס את האינדקס של המסמך ומציב אותו בתפריט ניווט מהיר
  • ALT + i – כיבוי והדלקת מידע זה
  • ALT + m – מעבר מהיר לתפריט הנגישות
  • ALT + s – מעבר לתפריט ניווט מהיר
  • ALT + 1 – חזרה לדף הבית
  • ALT + 2 – מעבר לתפריט הראשי
  • ALT + 3 – מעבר לתוכן המרכזי בעמוד
  • ALT + 4 – מעבר לחיפוש כללי
  • ALT + 5 – מעבר לדף יצירת קשר

במידה ועוברים בין דפים באתר המידע לגבי הבחירות שביצענו נשמר וממשיך עם הגולש אל הדף הבא